EXECUTING AGENCY: Hellenic Air Force/ Directorate of Works

TIME OF COMPLETION: 1989 - 1991

FINANCIAL SCOPE OF WORK : 836.900.000 GRD

The project was the construction of an integrated industrial complex building for disassembly and plating of aircraft's metal components in the air base Araxos.

The project included the building works and electromechanical works (new substation, fire extinguishe, portal cranes, etc.).
The Auction was made by the system Design - Construction.

*in joint venture.