EXECUTING AGENCY: Water Supply Corporation

PERIOD OF COMPLETION: 1991-1995

BUDGET: 1.012.844.570 GRD

Elevation by 1.65 meters of the walls of the channel Mornos in length of 1200 meters and static reinforcement of the free wall of the waterways by installing prestressed tendons in the concrete walls, the widening of access roads, the construction of two bridges resting on 370 micropiles and construction of the bridge with span of 12 meters. For the completion of the project required a total of 5,000 m3 of concrete, 2650 prestressed tendons with an average length of 10 meters and a maximum length of 23 m and 370 micropiles of 6 and 9 meters length.
The project was tendered a public call.

* in joint venture