EXECUTING AGENCY: DIRECTORATE OF TECHNICAL SERVICES PIRAEUS PREFECTURE

TIME OF COMPLETION: 1997-2001

BUDGET: 500.000.000 GRD

Design and Construction (earthworks and civil engineering works) coastal section of road connecting the Old Epidaurus with Galata and namely from the K.P. 6+000 km to the K.P. 7+300. By the construction of this section is completed the largest part of the above mentioned route and achieved thus the minimizing of the distance and time connecting the region Galatas - Poros.
The road, passing through rocky soils in total, with very high slope gradients and the structure is characterized particularly difficult.
The project was tendered in competition with the system of Design - Construction.