EXECUTING AGENCY: ERGA O.S.E. S.A.

TIME OF COMPLETION: 1999-2001

BUDGET: 8.500.000.000 GRD

Description: Works for the construction of the railway bridge that has 800m length and overlaps the river Axios. This construction included:

  1. The construction of piers which was based on eight pillars each.
  2. The installation of four pre-stressed concrete beams on each pier. Every beam has 32meters length.
  3. The construction of the concrete slab for the laying of the railway line
  4. The construction by the same methodology of three smaller bridges on the two sides of the main bridge. Those small bridges have length 50 to 150 meters
  5. Construction of sub grade of 3 to 8 meters high for the laying of the railway line in length of 8 Km.

*in joint venture