EXECUTING AGENCY: O.S.E. S.A.

TIME OF COMPLETION: 2002 - 2004

BUDGET: 11.479.677 €

Works for complete renewal of the railway line with length of 20 km that included:

  • the composition of geodetic measured drawings of the existing line followed by submission of improvement proposals
  • the unpick of the existing line,
  • the excavation of the existing ballast and the sub grade layer,
  • the electrical welding of rails UIC54,
  • the distribution of these rails,
  • the lying of sleepers B70 and rails UIC54 in length of 90 meters with special equipment,
  • the ballast laying,
  • the arrange of the geometry with tamping machine and with ballast regulator machine,
  • the aluminothermic welds and rail stressing,
  • the construction of small civil works.