EXECUTING AGENCY: O.S.E. S.A.

TIME OF COMPLETION: 2002-2004

BUDGET: 11.479.677 € 

The project involved firstly the composition of geodetic measured drawings of the existing line accompanied by submission of improvement proposals. Then works for complete renewal of the railway line with length of 19 km took place, that included:

  • the dismantling of the existing line,
  • the excavation of the existing ballast and the sub grade layer,
  • the electrical welding of rails UIC54,
  • the distribution of these rails,
  • the lying of sleepers B70 and rails UIC54 in length of 90 meters with special equipment,
  • the ballast laying,
  • the arrange of the geometry with tamping machine and with ballast regulator machine,
  • the aluminothermic welds and rail stressing
  • the construction of small civil works.