EXECUTING AGENCY: O.S.E. S.A.

PERIOD OF COMPLETION: 2002/2007

BUDGET: 11.517.038 €

Description: Works for the upgrade of the railway line, between time intervals of 3,5 hours. The works included:

  • conversion of the line, from jointed track to continuous weld rail (CWR) track,
  • aluminothermic welds,
  • rail stressing,
  • ballast cleaning,
  • refilling of the rails in the old welds,
  • cleaning of the ditches,
  • replacement of the old fastening system with new VOSSLOH and
  • lining and leveling in length of 100 km with mechanical means.

*in joint venture