EXECUTING AGENCY: HELLENIC RAILWAYS (O.S.E.) S.A.

PERIOD OF COMPLETION: 2005-2006

BUDGET: 523.937 € 

Description: Works for interventions included:

  • the change of the rail fastening material in 16 Km,
  • the tightening of rail fastenings in 26 km
  • the arrange of the geometry with tamping machine and
  • formation of ballast with ballast regulator machine in 12km.