EXECUTING AGENCY: O.S.E. S.A.

PERIOD OF COMPLETION: 2007-2009

BUDGET: 30.000.000 € 

Works for complete renewal of the railway line with length of 32 km. Among these the 8,2 Km was constructed between time intervals of 6,5 hours. The rest 24,8 Km was renewed by diversion of the circulation to new temporary bypass line. The renewal works included:

  • the composition of geodetic measured drawings of the existing line followed by submission of improvement proposals,
  • the dismantling of the existing line,
  • the excavation of the existing ballast and the sub grade layer,
  • the electrical welding of rails UIC54,
  • the distribution of these rails,
  • the lying of sleepers B70 and rails UIC54 in length of 108 meters with special equipment,
    · the ballast laying,
  • the arrange of the geometry with tamping machine and with ballast regulator machine,
  • the aluminothermic welds and rail stressing,
  • the supply and placement of new turnouts UIC54,
  • the construction of small civil works.