EXECUTING AGENCY: O.S.E. S.A.

PERIOD OF COMPLETION: 2007-2009

BUDGET: 15.000.000 €

Works for complete renewal of the railway line with length of 17 km, between time intervals of 6,5 hours that included:
· the composition of geodetic measured drawings of the existing line followed by submission of improvement proposals

  • the dismantling of the existing line,
  • the excavation of the existing ballast and the sub grade layer,
  • the electrical welding of rails UIC54,
  • the distribution of these rails,
  • the lying of sleepers B70 and rails UIC54 in length of 90 meters with special equipment,
  • the ballast laying,
  • the arrange of the geometry with tamping machine and with ballast regulator machine,
  • the aluminothermic welds and rail stressing
  • the supply and placement of new turnouts UIC54
  • the construction of small civil works.